How does adjudication work on a Calgary dispute?

Question

How does adjudication work on a Calgary dispute?

Answer from Construction Brain

Adjudication is a fast dispute process under Alberta's Prompt Payment and Construction Lien Act for payment disputes on construction contracts. An adjudicator decides the dispute on a short, fixed timeline, without a court hearing.

How the process works

A party starts adjudication with a notice of adjudication. Under Alberta's Prompt Payment and Adjudication Regulation, the parties have 4 calendar days to agree on an adjudicator; if they do not, a nominating authority appoints one within 7 calendar days. Alberta's page on its prompt payment rules names ARCANA and ADACC as nominating authorities, and parties can pick one when the contract is signed. The response is due within 12 calendar days, and the adjudicator must decide "within 30 days of receiving the documents," with extensions limited to a maximum of 10 calendar days. Adjudication cannot be started if the notice is given more than 30 days after the date of final payment.

What it covers. The regulation lists the matters that can go to adjudication: the valuation of services or materials, including change orders; payment under the contract, including change orders; disputes under a notice of non-payment; payment or non-payment of the major or minor lien fund; and "any other matter" the parties in dispute agree to.

How binding it is. The determination is binding unless a court directs otherwise, an arbitrator makes an award, or the parties settle the matter in a written agreement. Once registered with the court, it has the same effect as an order of an Alberta court. We found no exclusion for homeowner contracts in the Act.

The payment rules around it. An owner must pay a proper invoice no later than 28 days after receiving it, or give notice of a dispute within 14 days. That Act also requires the owner to retain a 10% lien holdback for 60 days from substantial performance or completion of the contract.

If adjudication does not fit the dispute, civil claims go to the Alberta Court of Justice civil division or, above its monetary limit, the Court of King's Bench; check the current limit with the court. Deadlines here are short, so keep the contract, invoices, change orders and notices together from the start and get legal advice early. You can describe your project through the Calgary Construction Network to be matched with local contractors.

Calgary Construction Network

Construction Brain — Built by a licensed contractor with 20+ years in the field. Powered by AI with strict guidelines and real building knowledge.

Ready to Start Your Project?

Get a free, no-obligation estimate for your Calgary renovation. Our team at CCN is ready to help bring your vision to life.

Contact Us